Watershed Management Implementation Non-Government Organization (WSM-NGO) for Khagrachari District
TUS • Environment & Natural Resource Management

Watershed Management Implementation Non-Government Organization (WSM-NGO) for Khagrachari DistrictWSM-NGO / CRLIWM-CHT

ProjectsEnvironment & Natural Resource Management
Project Status
active
Project Duration
22 Jun, 2026 - 30 Jun, 2030
Funded By
Asian Development Bank (ADB)
Coverage
Khagrachari Hill District; target coverage of 60 villages across 3 watersheds. Initial project/sub-watershed offices are in Khagrachari, Dighinala and Panchari; August 2026 field implementation focused particularly on the Dighinala WSM component.
Watershed Management Implementation Non-Government Organization (WSM-NGO) for Khagrachari District

The Watershed Management Implementation Non-Government Organization (WSM-NGO) for Khagrachari District is a 48-month assignment under the Climate-Resilient Livelihood Improvement and Watershed Management in the Chittagong Hill Tracts (CRLIWM-CHT) Sector Project. The contract was signed on 22 June 2026. The assignment is being implemented by Trinamul Unnayan Sangstha (TUS) as Lead NGO in Joint Venture with Kabidang.

The TUS Joint Venture supports the Project Management Office (PMO) and District Project Management Office (DPMO) in implementing community-prioritized watershed management sub-projects across three watersheds in Khagrachari District. The implementation approach emphasizes community ownership, gender equality, social inclusion, environmental sustainability, climate resilience, and environmental and social safeguard compliance.

Key Areas of Work

  • Community mobilization and inclusive participation through Para Development Committees (PDCs), Village Common Forest (VCF) Committees and other community groups.
  • Institutional and technical capacity building for community organizations and stakeholders.
  • Participatory planning, site selection, technical support, conservation measures, and environmental and social safeguards.
  • Promotion of sustainable and climate-resilient livelihoods.
  • Coordination with PMO, DPMO, PISC, local government institutions, traditional leaders and other stakeholders.
  • Systematic monitoring, reporting, documentation of lessons learned and knowledge sharing.
  • Strengthening operation and maintenance systems for the long-term sustainability of interventions.

Implementation Approach

The project combines participatory community processes with technical tools such as KoboToolbox, GPS-based site identification and verification, door-to-door field visits, participatory assessments and local knowledge. During August 2026, implementation focused particularly on the Dighinala WSM component, including community orientation, household and intervention-site identification, and coordination with PDCs, WSM Committees, local leaders, PMO and DPMO.

Project Reference

RFP: Package No. CRLIWM/SD-39
ADB Package: CHT/NGO/WSM/KHAG/SD-07
Contract Date: 22 June 2026
Project Duration: 48-month assignment (June 2026 – June 2030)

Project at a Glance

  • Executing Agency: Chittagong Hill Tracts Regional Council (CHTRC), with implementation through PMO and DPMO under the CRLIWM-CHT Sector Project (ADB Loan No. 4333).
  • Contract: Signed on 22 June 2026; the inception report describes a 48-month assignment covering June 2026 to June 2030.
  • Lead NGO and JV Partner: Trinamul Unnayan Sangstha (TUS), Lead NGO, in Joint Venture with Kabidang.
  • Target Coverage: 60 villages across 3 watersheds in Khagrachari Hill District.
  • Initial Staffing: 15 full-time Key and Non-Key staff (6 Key Experts and 9 Non-Key Experts) onboarded on 22 June 2026.
  • Initial Offices: Project/sub-watershed field offices identified for Khagrachari, Dighinala and Panchari.

Core Objectives

  • Mobilize communities and strengthen inclusive Para Development Committees (PDCs) and Village Common Forest (VCF) Committees.
  • Build organizational, managerial and technical capacity for participatory planning, project management, accounting, record keeping, technical supervision and post-construction O&M.
  • Provide technical support for watershed interventions, feasibility assessment, VCF profiling and mapping, soil conservation, and environmental and social safeguard compliance.
  • Improve climate-resilient livelihood opportunities for smallholder farmers and vulnerable households.
  • Maintain close coordination with PMO, DPMO, PISC, local government institutions, traditional leaders, technical experts and other stakeholders.
  • Maintain systematic monitoring, reporting, documentation, learning and dissemination of good practices and success stories.
  • Strengthen long-term sustainability through O&M systems, community ownership and institutional linkages.

Technical and Social Approach

The project follows a participatory, inclusive and community-driven watershed-management approach combining ecosystem restoration, soil and water conservation, agroforestry, sustainable agriculture, climate-resilient livelihoods and community infrastructure. Participatory Rural Appraisal tools, community validation and technical feasibility assessment are used to support demand-driven planning.

Safeguard compliance is integrated throughout implementation. The inception framework calls for Free, Prior and Informed Consent (FPIC) for Indigenous communities, environmental and social screening of interventions, use of EMP/SMP measures where required, and at least 40% women's representation in PDCs and VCF Committees.

Monitoring, Evaluation and Learning

The MEL approach includes participatory monitoring, baseline surveys, mid-term evaluation, quantitative and qualitative data collection, environmental/social/IP safeguard monitoring, joint monitoring with PMO/DPMO/PISC, financial tracking, and documentation of lessons learned and innovations. Required reporting includes inception, monthly, quarterly, six-monthly, annual and project completion reports.

Governance and Quality Assurance

The inception arrangement proposes a five-member Project Implementation Committee (PIC) led by the Executive Director of TUS, with the Executive Director of Kabidang, the WSM Project Coordinator/Team Leader, a PDC/VCF representative and a DPMO representative. The structure is intended to provide oversight for implementation quality, monitoring, coordination and accountability.

Project at a glance

Project Profile

CoverageKhagrachari Hill District; target coverage of 60 villages across 3 watersheds. Initial project/sub-watershed offices are in Khagrachari, Dighinala and Panchari; August 2026 field implementation focused particularly on the Dighinala WSM component.
PriorityHigh
Results & performance

Project Progress & Results

Headline Indicator

Target villages

Target: 60 villages
The inception report records a total target coverage of 60 villages across three watersheds.
Headline Indicator

Target watersheds

Target: 3 watersheds
The assignment covers three watersheds in Khagrachari Hill District.
Achievement

Notice to Award issued

Actual: Completed
Notice to Award issued on 21 June 2026.
Achievement

WSM-NGO contract signed

Actual: Completed
Contract signed with PMO, CHTRC on 22 June 2026.
Achievement

Project office established

Actual: Completed
Project office established at Marma Samsad Building, Pankhaiyapara on 22 June 2026.
Achievement

Initial project team onboarded

Actual: 15 staff Target: 15 staff
Six Key Experts and nine Non-Key Experts were onboarded on 22 June 2026.
Achievement

Project staff orientation completed

Actual: Completed
Project orientation with staff completed on 23 June 2026.
Achievement

Organizational policy orientation completed

Actual: Completed
Orientation covered HR, financial management, gender, child protection, PSEA, safeguarding, MEAL and Code of Conduct on 24 June 2026.
Achievement

Inception Report submitted

Actual: Completed
Inception Report prepared and submitted on 24 June 2026.
Achievement

Para Group reformation facilitated

Actual: 27 Para groups
Facilitation support completed for 27 Para Group reformations with 696 participants: 351 male and 345 female.
Achievement

PDC / Para orientation participants

Actual: 701 participants
Orientation of CRLIWM PDCs / Para Orientation Meetings completed with 350 male and 351 female participants.
Achievement

Para Nari Development Group participation

Actual: 135 female participants
Formation of Para Nari Development Group (PNDG) completed with 135 female participants.
Achievement

Dighinala WSM coordination meeting participants

Actual: 36 participants
One Dighinala WSM coordination meeting completed with 27 male and 9 female participants.
Achievement

Transforming jhum to agriculture sites identified

Actual: 14 households
Potential sites identified with 14 households, covering 15 acres.
Achievement

Fruit tree plantation sites identified

Actual: 37 households
Potential fruit tree plantation sites identified with 37 households.
Achievement

Orchard management sites identified

Actual: 42 households
Potential orchard management sites identified with 42 households, covering 20 acres.
Achievement

Drainage improvement sites identified

Actual: 4 sites
Potential drainage improvement sites identified, covering 65 acres.
Achievement

Forest silviculture operation sites identified

Actual: 17 sites
Potential forest silviculture operation sites identified, covering 50 acres.
Achievement

Disaster-affected river and agricultural land sites identified

Actual: 3 sites
Potential sites identified for disaster-affected rivers and agricultural land, covering 5 acres.
Achievement

Landslide treatment sites identified

Actual: 10 sites Target: 5 sites
Potential landslide treatment sites identified.
Achievement

Gully treatment sites identified

Actual: 3 sites Target: 5 sites
Potential gully treatment sites identified.
Achievement

Buried-pipe irrigation improvement sites identified

Actual: 4 sites / metres Target: 5000 sites / metres
Four potential irrigation canal improvement sites (buried piping) identified; the report records a 5,000 metre target.
Achievement

Regenerative farming households selected

Actual: 54 households Target: 54 households
Households selected for regenerative farming support including vermicomposting, fruit bagging and pheromone traps.
Achievement

Homestead improvement households selected

Actual: 58 households Target: 54 households
Households selected for homestead improvement support.
Achievement

New dam construction sites selected

Actual: 8 sites Target: 7 sites
Sites selected for new dam construction.
Achievement

Dam reconstruction sites selected

Actual: 5 sites Target: 5 sites
Sites selected for dam reconstruction.
Achievement

Pond re-excavation sites selected

Actual: 24 sites Target: 19 sites
Sites selected for pond re-excavation.
Achievement

Wetland improvement sites selected

Actual: 1 site Target: 1 site
Site selected for wetland improvement.
Achievement

Tube well sites selected

Actual: 3 sites Target: 7 sites
Sites selected for tube wells.
Achievement

Tube well with piping network sites selected

Actual: 14 sites Target: 9 sites
Sites selected for tube wells with piping networks.
Achievement

New irrigation canal sites selected

Actual: 8 sites / metres Target: 2050 sites / metres
Eight sites selected for new irrigation canal interventions; the report records 2,050 metres.
Achievement

Solar lighting households identified

Actual: 224 households Target: 204 households
Potential beneficiary households identified for solar lighting systems.
Where we work

Project Coverage Map

1 District 1 Upazila
Khagrachari District - WSM-NGO Target Area
Khagrachari
District-level target coverage recorded in the inception report: 60 villages across 3 watersheds. Initial project/sub-watershed offices are identified in Khagrachari, Dighinala and Panchari.
Dighinala WSM Component
Khagrachari → Dighinala
Initial coverage record from the August 2026 monthly report. The overall assignment covers three watersheds in Khagrachari District; the report specifically identifies Dighinala as the focus of August 2026 field implementation.